next release schedule - 5 weeks?

Aaron Bentley aaron.bentley at utoronto.ca
Tue Mar 27 04:30:59 BST 2007


-----BEGIN PGP SIGNED MESSAGE-----
Hash: SHA1

Martin Pool wrote:
> Counting this week as the first week of development we would have
> 
> 26 Mar   open week 1
> 2 Apr    open week 2
> 9 Apr    open development week 3
> 16 Apr    bugfixes only
> 23 Apr     release candidate
> 30 Apr     release
> 
> Would that be acceptable?

5 weeks is fine by me.  Does development on 0.17 start on April 23 then?

> I'd be happy to be release manager again for this cycle, unless
> someone else is particularly keen.

Be my guest.  I'd be interested in doing a release at some point in the
future.

Aaron