Juju 1.17.1 milestone
Martin Packman
martin.packman at canonical.com
Thu Jan 23 10:55:11 UTC 2014
On 21/01/2014, Curtis Hovey-Canonical <curtis at canonical.com> wrote:
>
> I believe milestone 1.17.1 has about 4 weeks of issues targeted to it.
> https://launchpad.net/juju-core/+milestone/1.17.1
I have retargetted all bugs that are not actually landed or about to
land on trunk against the new 1.18.0 milestone. This should mean we
can get a 1.17.1 release done, as desired.
In general, I think we should target bugs against the next stable
release milestone for planning, and only move them to the upcoming
development release milestone when there's actually a prospect of
something landing. Others may have a different opinion on this.
For now, if you land something in time for 1.17.1 please bump the
related bug back to that milestone.
> I doubt we can release a 1.18.0 this month without cutting scope. That
> may not be possible as API-everywhere really must be complete to
> release 1.18.0.
Playing with milestones hasn't changed the fact we have a lot of work
targeted at 1.18, unfortunately not much jumped out at me as
deferrable.
Martin