> 1) Describe the planned release dates, and get everyone to agree to get
> back into a time-based release schedule. Martin's idea was to have:
> 
>   freeze 28 August
>   1.7rc1  4 September
>   1.7    11 September
> 
> This gives us 2 weeks of open development for the 1.7 release cycle.
> Which should be plenty.

While writing up This Week in Bazaar, we realized that releasing on 9/11
is a bit weird for the US, and releasing on a Wed is weird in general.
I'm *very* hesitant to postpone a delay, so what about releasing 1.7 on
Monday night Sept 8th. That will get us back to the "release just after
a weekend, after John and Aaron have had a day to respond to anything
that cropped up over the weekend". (Robert, Martin, Ian and Andrew
having already had a working day in AU.)

So unless people object, I'm going to be bumping all those dates back 3
days, to make them:

  	freeze	25 Aug
	1.7rc1	 2 Sept (1 Sept is Labor day in US)
	1.7	 8 Sept

John
=:->
-----BEGIN PGP SIGNATURE-----
Version: GnuPG v1.4.9 (Cygwin)
Comment: Using GnuPG with Mozilla - http://enigmail.mozdev.org

iEYEARECAAYFAkikj6AACgkQJdeBCYSNAAP8lACfZOr1SRUclfOpTlRmwKOzo197
ANEAmwUFnldHAIVdtvvLcga8hx8/Trsi
=mK6n
-----END PGP SIGNATURE-----



More information about the bazaar mailing list