Release Schedule for the Gutsy Gibbon

Scott James Remnant scott at ubuntu.com
Thu Apr 12 09:26:52 BST 2007


In contrast to previous releases where we've decided the schedule during
UDS, we have planned the schedule for gutsy in advance:

	https://wiki.ubuntu.com/GutsyReleaseSchedule


The schedule is as for feisty, with the following alterations:

 - there are 6 milestone releases; initially spaced three weeks apart,
   then moving to two weeks apart from FeatureFreeze onwards.

 - the developer sprint is a little earlier in the process, this was to
   accommodate dates of conferences and known developer holidays.

 - BetaRelease is one week after the release of GNOME 2.12.0

 - FinalRelease is three weeks after Beta, instead of the usual four;
   this is to allow us to release on October 18th.  We will release with
   as many of the GNOME 2.12.1 fixes as possible.

Scott
-- 
Scott James Remnant
Ubuntu Development Manager
scott at ubuntu.com
-------------- next part --------------
A non-text attachment was scrubbed...
Name: not available
Type: application/pgp-signature
Size: 189 bytes
Desc: This is a digitally signed message part
Url : https://lists.ubuntu.com/archives/ubuntu-devel-announce/attachments/20070412/010a342f/attachment.pgp 


More information about the ubuntu-devel-announce mailing list